Belmont High School

Polar Park
September 26, 2019

Skanska USA Building awarded WLF the site enabling contract for the proposed renovations and additions to Belmont High School.

The work includes installing temporary site fencing and barriers, site demolition, import of 22,500 ton of material for create temporary work platforms and access for the follow on building construction.

Major utility relocation work includes 4,000 LF of water pipe, 500 LF of sewer and 7,200 LF of underground duct banks.

This project adds to our educational portfolio of work in the Town of Belmont having previously completed the site work for the Roger Wellington Elementary School and the Burbank Elementary School.

Work is scheduled to begin in mid-June 2019 and continue on through the summer.